ATH Resource Authorization
To specify resource authorizations (i.e., finished labor, material, etc.) in the planning schedule.
Position
Element
Name
Type
Requirement
Min
Max
Repeat
Code identifying the resource which the buyer is authorizing the seller to commit to.
It is imperative that negotiations defining "Financial Commitment" have previously occurred and are agreed to by both buyer and seller.
Date (YYMMDD).
R0203: At least one of ATH-02 or ATH-03 is required
ATH02 - resource authorization through-date: The date through which the buyer authorizes the seller to commit the resource defined in element ATH01.
Numeric value of quantity.
C0305: If ATH-03 is present, then ATH-05 is required
ATH03 - current cumulative requirements quantity: The cumulative quantity that has been authorized to-date from the cumulative start date (ATH05) through the resource authorization through-date (ATH02).
Numeric value of quantity.
C0405: If ATH-04 is present, then ATH-05 is required
ATH04 - Maximum Cumulative Requirements Quantity: The maximum cumulative quantity that has been authorized to-date from the cumulative start-date (ATH05) through the resource authorization thru-date (ATH02). This is a high water mark. If the forecast decreases, the current cumulative requirements quantity also decreases, but the maximum cumulative requirements quantity does not decrease.
Date (YYMMDD).
ATH05 - cumulative start date: The date where the cumulative quantity count starts. This date might be the start date of a contract period, a calendar or fiscal year, or other.